In August Nvidia agreed to guarantee up to $105 billion in lease and power payments for a single Ohio data-center campus. It is not an investment but a capped residual-value guarantee, and Nvidia has disclosed neither the default probability, recovery value, nor discount rate behind its "not significant" fair-value conclusion. This issue walks five financing structures that landed in four months (guarantees, warrants, project vehicles, compute offtakes) and asks who is supposed to price any of them, reads Britain's Railway Mania as the closer precedent than the dot-com bust, and forecasts that the gap between disclosed ceilings and estimable expected loss widens through 2027.

Anchor figure

Nvidia's $105 billion capped residual-value guarantee carries no disclosed default probability, recovery value, or discount rate: the ceiling is public, the loss curve is not.

Key takeaways

Where it sits in the series

Moves the Grid-Silicon Order from the physical stack to the financing layer beneath it: the guarantees and warrants funding the buildout are as load-bearing, and as unpriced, as the equipment they pay for.

READ THE FULL ISSUE Published in full, free, on Beehiiv.

Forecasts this issue put on the watchlist

Open Financing
The guarantee gap widens, not narrows, through end-2027: the distance between gross disclosed maximum contingent exposure and what a diligent outsider can independently estimate as probability-weighted exposure.
Through end-2027
Open Financing
Rating-agency AI-guarantee research: any expected-loss methodology named at capped AI-vendor guarantees and applied to two or more issuers.
Quarterly
Open Financing
FSOC / BIS formal study status: whether the Financial Stability Oversight Council moves from "requested to study" to a published assessment of AI-debt systemic risk.
Quarterly
Open Financing
New deal structure count: of the next five major tracked AI-infrastructure financings, how many use transparently priced structures versus capped or conditional guarantees.
Per deal, as they land
Open Financing
KBRA AI-7 contingent-commitment tracker: whether a netted or probability-weighted figure appears alongside the gross ceiling.
Quarterly
Open Financing
Guarantee-call events: any disclosed instance of an AI-infrastructure guarantee actually being called.
As they happen
Open Grid Connections & Local Approval
Local-opposition project value: quarterly halted or blocked AI-datacenter project value.