FERC RM26-4 progression.
Resolved: missed
- Chokepoint
- Grid Connections & Local Approval — Interconnection queues, siting fights, and the regulatory dockets (FERC, state PUCs, SCCs) that decide them. (Mostly price, occasionally an outright no)
- Kill condition
- Advancing from advance notice to a notice of proposed rulemaking by mid-2026 federalizes cost-assignment and preempts patchwork state outcomes.
- Horizon
- Quarterly docket check
- Source
- Issue 6 — The New Utility · full issue
Why it is on the watchlist
Issue 6’s version of the RM26-4 test: advancing from advance notice to a proposed rule by mid-2026 would federalize cost assignment and preempt patchwork state outcomes.
How it resolved
Missed 2026-08-20. FERC did not issue the proposed rulemaking by mid-2026. It acted June 18, 2026 through §206 show-cause orders to all six RTOs instead — arguably a faster federal lever, but not the rulemaking this item forecast.
How Aroko tracks forecasts
Every item is reproduced from a published issue with its original kill condition intact. Status changes only on dated, citable evidence that meets that condition, reviewed weekly. Nothing is resolved in hindsight to improve the record.
Get the next forecast when it is published
Free. Biweekly. No sponsored research. Every forecast tracked in public with its kill condition attached.
GET THE LETTER